The facilities built as part of the project:
• 35 kV HV line from 35 kV «Central GTPP» - DNS-2 (booster pipeline pumping station) HV line to control station KP-71
• 35 kV HV line w/ 35 kV converter substation from 110 kV "Yarakta" substation to 35 kV substation of control station KP-79
• Two-circuit 110 kV "Rassoly — Yarakta" HV line

The three overhead lines have ensured the uninterrupted supply of electricity to the Yaraktinskoye oil and gas condensate field, the main asset of the Irkutsk Oil Company in the Irkutsk Region, where approximately 80% of hydrocarbons are produced.
Construction and erection works on the sites of Irkutsk oil company
Customer: INK LLC
Object type: electric grid construction
Location: Irkutsk Region
Completion period: February 2023 - May 2024